The gateways are the hard stops in the life of a higher-risk building. You cannot start construction without Gateway 2 approval. You cannot occupy without a Gateway 3 completion certificate. Both are decided by the Building Safety Regulator. This page covers new higher-risk buildings. Building work to an existing, occupied building follows a related process, which we will cover on its own page.
- Gateway 2
- Building control approval for higher-risk buildings, last updated 1 October 2026 In force
- Gateway 3
- Applying for a completion certificate, last updated 1 October 2026 In force
- Decision periods
- Gateway 2: 12 weeks, SI 2023/909 reg 5. Gateway 3: 8 weeks, reg 41. Both extendable by written agreement
- Scope
- New higher-risk buildings. Work to existing, occupied buildings is not covered on this page
Planning Gateway One
The planning stage gateway requires a fire statement with planning applications for relevant high-rise residential development. A note of caution on terminology. “Gateway 1” now also refers to gateway assessments for local plans, which are a different thing. If you are searching for guidance, use the term Planning Gateway One.
Gateway 2: building control approval
The client must ensure approval is granted before any work starts. You may appoint an agent, but the legal responsibility does not move. Starting work without approval is a criminal offence.
Decision periods and what follows approval
- Up to 12 weeks for a new higher-risk building, unless an extension is agreed.
- Outcomes are approved, approved with requirements or rejected. There is a review route, then appeal to the First-tier Tribunal.
- Approval lapses if commencement is not reached within three years.
- Notice of intention to start: five working days beforehand. Notice of commencement: within five working days after.
Fire strategy and the fire and emergency file
Every Gateway 2 application for a new higher-risk building must include a fire and emergency file. This is set by Schedule 1, paragraph 5 of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023.
The file must set out:
- the matters considered when assessing how fire spread and structural failure could affect the building;
- the design proposals and approaches taken to meet the building regulations on those risks;
- the measures the owner should adopt so that everyone can be evacuated safely, including assumptions about who will live there;
- a plan of the fire and rescue service’s requirements for access and firefighting water; and
- a report showing how compliance with the building regulations on those risks will be achieved.
That is the substance of a fire strategy. The regulations do not use the words “fire strategy”. Government confirmed this in its Grenfell Tower Inquiry progress report of September 2026. It corrected an earlier statement and said a fire safety strategy is not a required document in its own right.
The Inquiry recommended making a fire safety strategy, produced by a registered fire engineer, a legal requirement at Gateway 2. It would then be reviewed at Gateway 3. Government has accepted this. It is reviewing how far the current rules already go and plans a working group with industry. Expect this to change.
Our view. Do not read the missing words as permission to leave a fire strategy out. Your fire strategy is the core of the fire and emergency file. An application without a coherent one is unlikely to give the regulator a file it can accept.
Sources: SI 2023/909 Schedule 1; Building Act 1984 s.120G; Grenfell Tower Inquiry progress report, September 2026, recommendation 10.
Gateway 3: the completion certificate
A full certificate on completion, or a partial one only where a partial completion strategy was submitted with the Gateway 2 application. That strategy cannot be retrofitted later.
The submission is substantial. It includes:
- latest drawings and plans;
- the construction control plan;
- the change control plan;
- the mandatory occurrence reporting plan;
- the building regulations compliance statement;
- the fire and emergency file;
- the change control log;
- drainage information;
- signed compliance declarations from each principal designer and principal contractor;
- a client confirmation statement;
- a signed handover statement to the responsible person under the Fire Safety Order and the principal accountable person; and
- since 1 October 2026, confirmation that the Building Safety Levy has been paid or is not payable.
The change log is where most projects are exposed. It has to reconcile what was approved with what was built.
Gateway 3 has a statutory period and practice runs well beyond it
GOV.UK guidance does not state one. The regulations do. Regulation 41 of SI 2023/909 requires the regulator to determine a valid completion certificate application within 8 weeks of receipt, or within a longer period agreed in writing. This page previously said no period was published. That was wrong and is corrected here.
The statutory figure is not a planning figure. The regulator’s own data for June to August 2026, published 15 September 2026, shows a median determination time of 20 weeks for completion certificates. It shows a median of 22 weeks for Gateway 2 approval on new higher-risk buildings against a 12-week statutory period. Programme on the evidence and expect to be asked to agree an extension.
Reform in train
The Construction Products Reform White Paper proposes bringing every construction product into regulatory scope and creating a Single Construction Regulator. That consultation closed in May 2026 and no response has been published.
Separately, the Building Safety Regulator’s consultation on Approved Document B closed on 1 July 2026. Government reports that “more than 500 responses were received, more than double the number received to the consultation on second staircases”. It adds that “given the volume and technical nature of the responses received, recommendations are expected by March 2027”.
For anyone designing now, the practical reading is that the guidance you are working to is the guidance that will apply for some time yet. Any change is unlikely to land before spring 2027.
Rejection is not the same as refusal
A Gateway 2 application passes through two distinct stages. Confusing them causes a lot of avoidable programme loss. First it is checked for completeness. Only if it passes that check does it reach substantive assessment.
An application rejected at the completeness stage never consumed assessment time. The decision period never started. In programme terms that is the expensive outcome, because the clock people planned around was never running. The most common causes are a missing document or an unsigned declaration.
Change control during construction
Gateway 2 approves a design. Buildings are not built exactly as designed. The regime anticipates this through the change control plan, which is submitted with the application and then operated throughout construction.
The discipline that matters is the change control log. At Gateway 3 the regulator reviews it and compares the approved design against what was built. A log that has been continuously maintained will be much stronger and more accurate. A log rebuilt near completion usually has gaps. The regulator will see them.
Three practical points follow. Decide at the start who owns the log and has authority to classify a change. Record changes as they are decided, not when they are built. Treat any change touching fire safety measures, compartmentation, escape routes or the external wall as significant until someone competent says otherwise.
The Gateway 3 submission, document by document
| Document | What it has to do |
|---|---|
| Latest drawings and plans | Show the building as built, not as approved |
| Construction control plan | How compliance was managed on site |
| Change control plan and log | Reconcile approved design against what was built |
| Mandatory occurrence reporting plan | How safety occurrences were identified and reported during construction |
| Building regulations compliance statement | The case that the works comply |
| Fire and emergency file | The information the future responsible person and principal accountable person will need |
| Drainage information | As required for the works |
| Signed compliance declarations | From each principal designer and principal contractor |
| Client confirmation statement | The client’s own confirmation |
| Signed handover statement | Handover to the Fire Safety Order responsible person and the principal accountable person |
| Building Safety Levy confirmation | That the levy has been paid or is not payable. The certificate cannot issue until the collecting authority confirms payment in full or a valid notice of no charge |
The regulator assesses these documents, compares them against what was agreed at Gateway 2, reviews the change log and inspects the completed work. The inspection is the part people most often underestimate. Inspectors look at the building itself, as well as the paperwork.
The handover is a real deliverable
The signed handover statement transfers information to the people who will carry the in-occupation duties. What is handed over at Gateway 3 becomes the foundation of the golden thread and, in due course, of the safety case report.
This is where design and construction meets occupation. Many existing buildings were failed by their own handover long before the Act existed. If you are the incoming principal accountable person, the handover is the single best opportunity you will ever get to obtain complete information about the building. It does not come round again.
Common questions
Can we start enabling works before Gateway 2 approval?
Building work on a higher-risk building cannot start before approval is granted and starting without it is a criminal offence. Whether a particular activity counts as building work is a question to resolve with your building control professional before anyone mobilises, not afterwards.
Who is responsible, the client or the agent?
The client. An agent may be appointed to act, but the legal responsibility for ensuring approval is granted before work starts does not transfer.
How long does Gateway 3 take?
Regulation 41 of SI 2023/909 sets 8 weeks from receipt of a valid application, or longer if agreed in writing. The regulator’s data for June to August 2026 shows a median determination time of 20 weeks, so plan on the evidence rather than the statutory period.
What happens if Gateway 2 approval lapses?
Approval lapses if commencement is not reached within three years. On a scheme that stalls for funding or planning reasons, that date needs tracking deliberately, because reaching it means going back through Gateway 2.
Does the levy affect the gateways?
Yes, at both ends. For a major residential development the regulator collects levy information from the Gateway 2 application and asks for floorspace figures with the commencement notice. At Gateway 3, the completion certificate cannot be issued until the collecting authority confirms that the levy has been paid in full or that a valid notice of no charge has been issued. This applies to applications made on or after 1 October 2026.