Every term with the provision that defines it, so you can check the source rather than take our word for it. Terms marked BS(W)A are Welsh and are mostly not yet in force.
| Term | Meaning | Source |
|---|---|---|
| Accountable person | A person holding a legal estate in possession in the common parts, or a person under a relevant repairing obligation for them. Managing a building does not make you one. | BSA 2022 s.72 · BS(W)A 2026 s.8 |
| Building assessment certificate | The certificate a principal accountable person must apply for when directed by the regulator, within 28 calendar days. Fee £312 plus assessment costs. Must be displayed prominently once issued. | BSA 2022 Part 4 |
| Building certificate | The Welsh equivalent, for occupied category 1 buildings. Not yet in force. | BS(W)A 2026 ss.42–45 |
| Building safety authority | In Wales, a county or county borough council designated by the Welsh Ministers, one for each fire and rescue authority area. None have been designated. | BS(W)A 2026 s.122 |
| Building Safety Regulator | A body corporate established on 27 January 2026. No longer part of the Health and Safety Executive. Non-Crown, sponsored by MHCLG. | SI 2026/20 reg 3(1) |
| Category 1, 2 and 3 building | The Welsh tiering. Category 1 is 18 metres or 7 storeys. Category 2 is below that but at least 11 metres or 5 storeys. Category 3 is below 11 metres and fewer than 5 storeys. | BS(W)A 2026 s.6 |
| Category A and B work | Classification of work to an existing higher-risk building. Category A covers height, width, storeys, layout, unit numbers, fire safety measures, staircases, escape routes and common parts. Misclassification is a common cause of rejection. | Gateway 2 guidance |
| Golden thread | The requirement that building safety information is accurate, accessible to those who need it and kept up to date through change. An information standard, not a storage product. | BSA 2022 Part 4 |
| Higher-risk building | In England, at least 7 storeys or 18 metres with at least 2 residential units. Hospitals and care homes are in scope for design and construction but not the in-occupation regime. | BSA 2022 |
| Key building information | Information that must be supplied within 28 days of submitting a registration application. | Registration guidance |
| Landlord’s certificate | The certificate a landlord uses to establish what it may recover from a qualifying leaseholder. It shows whether the landlord is responsible for the defect, met the contribution condition or is connected to the developer. Due within four weeks of a leaseholder request, a notice of sale, awareness of a new defect, or any remediation service charge demand. If a compliant certificate is not provided, the protective condition is treated as met and no service charge is payable. | SI 2022/711 regs 5 to 7 |
| Leaseholder deed of certificate | The prescribed deed by which a leaseholder establishes that their lease qualifies. The landlord must allow at least eight weeks to reply. If no reply arrives, it must send a second notice and telephone the leaseholder. It may not charge for the deed or the notices. | SI 2022/859 reg 6 and the Schedule |
| Major residential development | For the levy, at least 10 dwellings or at least 30 purpose-built student accommodation bedspaces. Where the building already contains them, this is measured as a net increase. | SI 2025/1236 reg 6 |
| Mandatory occurrence reporting | The duty to report specified safety occurrences. In Wales the equivalent is an occurrence recording system under section 38. | BSA 2022 Part 4 |
| Named client | The person liable for the Building Safety Levy, defined per application type in Schedule 4. | SI 2025/1236 reg 22 |
| Permitted maximum | The lifetime cap on what a qualifying leaseholder can be charged towards relevant measures. It is £15,000 in Greater London and £10,000 elsewhere. It rises to £50,000 where the lease was valued over £1m and £100,000 over £2m. No more than one tenth may be charged in any twelve month period. | BSA 2022 Sch.8 paras 6 and 7 |
| Principal accountable person | Where there is one accountable person, that person. Where there are several, the one holding the estate in or repairing obligation for the external structure, meaning the foundations, external walls and roof. | BSA 2022 s.73 · BS(W)A 2026 s.9 |
| Qualifying lease | A long lease of a single dwelling in a relevant building, granted before 14 February 2022, where the tenant pays a service charge. At the qualifying time, the dwelling must have been the tenant’s only or principal home, or the tenant owned no more than two other UK dwellings. The three conditions are alternatives, not a combined test. | BSA 2022 s.119 · s.119A |
| Regulated building | In Wales, a building containing at least 2 residential units, wholly or mainly in Wales, excluding Schedule 1 descriptions. No height threshold. | BS(W)A 2026 s.2 |
| Relevant building | For the leaseholder protections, a self-contained building or part of a building with at least two dwellings. It must be at least 11 metres high or at least 5 storeys. Lower than the higher-risk threshold, so a building can fall outside the safety case regime and inside the protections. | BSA 2022 s.117 · s.118 |
| Relevant defect | A defect arising from work done in the 30 years to 28 June 2022 that causes a building safety risk. That means a risk to people in or about the building from the spread of fire or the collapse of all or part of the building. | BSA 2022 s.120 |
| Relevant HMO | A house in multiple occupation in Wales within the Housing Act 2004 Part 1 meaning, excluding section 257 converted blocks and the section 78(3) exclusions. Part 2 duties are not yet in force. | BS(W)A 2026 s.78 |
| Resident engagement strategy | The strategy for engaging residents on building safety decisions. In Wales it extends to occupied category 2 buildings. | BSA 2022 Part 4 · BS(W)A 2026 ss.40–41, 46 |
| Safety case | The body of evidence about a building’s risks and their control. Distinct from the report that summarises it. | Practice term |
| Safety case report | The document making the argument that risks are understood and controlled. In Wales it must be sent to the building safety authority. In England the regulator calls it in. | BSA 2022 s.85 · BS(W)A 2026 s.37 |
| Special measures manager | A manager appointed for a category 1 building where duties are not being met. Not yet in force. | BS(W)A 2026 s.109 and Sch 2 |