Nobody in this market publishes their fees. We checked the major providers and none of them state a price, a range or even what drives one. Here is what we do know. The regulator’s charges are published. So are the statutory timescales. We can also show how long things are taking in practice.
- Charges
- Building Safety Regulator Charging Scheme 2026 to 2027, for the year from 1 April 2026 In force
- Hourly rate
- £156 per hour worked by regulator staff
- Registration
- £251 per building, SI 2023/315 reg 20
- Certificate application
- £312, plus hourly assessment charges and third-party costs
- Caveat
- Assessment processing is running at twice the regulator’s initial expectation
The regulator’s charges
These are payable to the Building Safety Regulator regardless of who carries out your technical work. Most are now a fixed charge on submission plus an hourly charge for the time regulator staff spend on the case. Any costs the regulator incurs from relevant authorities and third parties are added on top.
| Charge | Amount | Charging scheme |
|---|---|---|
| Registering a high-rise residential building | £251, plus third-party costs | Schedule 14 |
| Building assessment certificate application | £312, plus £156 per hour and third-party costs | Schedule 15. Payable by the principal accountable person |
| Review of a regulator decision, including registration and certificate decisions | £312, plus £156 per hour and third-party costs | Schedule 26. Refunded or exempted if the review finds in your favour |
| Building control approval application, Gateway 2 | £195, plus hourly charges | Charged upfront with the application |
| Completion certificate application, Gateway 3 | £234, plus hourly charges | Schedule 10 |
One conflict worth knowing about. The GOV.UK page on registering a building, last updated 25 March 2025, still says a review costs £302. The charging scheme for 2026 to 2027 sets £312 plus hourly charges. The charging scheme is the later document, so budget on it.
The hourly element is the part that varies. It varies with the quality of what you submit. Every request for further information, every clarification call and every reassessment after a refusal is regulator time. Regulator time is charged.
A submission that answers the regulator’s questions before they are asked is cheaper to have assessed. It is also more likely to succeed.
The statutory timescales
| Step | Period | Source |
|---|---|---|
| Key building information after registration | 28 days | From submitting the registration application, per GOV.UK |
| Applying for a building assessment certificate | 28 days | From the day the direction is given, s.79(2). Failing to apply without reasonable excuse is an offence, s.79(3) and (4) |
| Requesting a review of a regulator decision | 21 relevant days | From the day the decision is made, SI 2023/315 reg 23(3). Relevant days exclude Christmas Day, Good Friday and bank holidays, not weekends |
| Regulator decides the review | 28 relevant days | From receiving the notice, SI 2023/315 reg 23(5) |
| Gateway 2, new higher-risk building | 12 weeks | SI 2023/909 reg 5, or longer if agreed in writing |
| Gateway 2, work to an existing building | 8 weeks | SI 2023/909 reg 13, or longer if agreed in writing |
| Gateway 3, completion certificate | 8 weeks | From receipt of a valid application, SI 2023/909 reg 41, or longer if agreed in writing |
| Building assessment certificate decision | None set | Neither the Act nor the regulations set a decision period |
| Certificate reassessment | Around 5 years | The regulator’s stated aim, not a statutory cycle. Sooner after significant change, an incident or a safety concern |
Note the Gateway 3 entry. GOV.UK guidance does not state a decision period for completion certificates and this page previously said none was published. The regulations do set one. Regulation 41 of SI 2023/909 requires a valid application to be determined within 8 weeks of receipt, unless a longer period is agreed in writing.
Statute against practice
Every gateway period carries the words “or within such longer period as the regulator and the applicant agree in writing”. In practice that clause matters more than the period itself. The regulator’s own figures show how far real decision times sit from the statutory ones.
| Decision | Statutory period | What the regulator reports |
|---|---|---|
| Gateway 2, new higher-risk building | 12 weeks | Median approval time of 22 weeks, down from 43 weeks a year earlier |
| Gateway 3, completion certificate | 8 weeks | Median determination time of 20 weeks |
| Building assessment certificate | None set | Processing twice as long as initially expected. 66% of applications refused so far in 2026 |
The gateway figures are from the regulator’s building control approval application data for June to August 2026, published 15 September 2026. The certificate figures are from its statement of 9 July 2026. Treat the published period as the minimum and expect to be asked to agree an extension.
The same statement said the regulator would prioritise applications already under assessment. It would call in new applications only when necessary until improved processes are agreed. It would also explore fast-track reassessment for previously refused certificates once standards are met. If you have not yet been directed to apply, spend the time getting the evidence right rather than waiting for the letter.
What drives the cost of the work itself
We are not going to publish a price list. A safety case for a 1960s large panel system block with unresolved remediation history is a different job from one for a 2019 build with a complete handover pack. Any firm quoting one figure for both is guessing at your expense. What we can do is tell you what moves the number.
- Whether the evidence exists. This dominates everything else. A building with original drawings, a clean compartmentation survey and closed-out fire door actions costs a fraction of one where the evidence must be created from scratch.
- Structural history. Large panel system construction, unresolved remediation or any history of structural problems pulls in specialist structural input that a straightforward frame does not.
- External wall systems. Whether you hold a current, adequate assessment. Whether remediation is complete, in progress or undecided.
- Number of accountable persons. Several means several risk assessments to reconcile. It also means information-sharing arrangements to evidence rather than describe.
- Portfolio effects, in your favour. The second building costs materially less than the first, because the management system work is done once.
- Whether you have been refused before. A re-application against a contravention letter is a different job from a first submission.
Budgeting the whole cost
The report is usually the smallest of three cost lines. It is also the one most often budgeted in isolation.
- Regulator charges. The fixed charges above, plus hourly assessment time that grows with every request for information and every resubmission.
- Evidence creation. Surveys, intrusive investigations, structural and fire engineering input and remedial work to close out findings. On older buildings this is normally the largest line.
- Your own time. Accountable person, managing agent and resident engagement effort to run the safety management system the report describes. The regulator assesses whether that system works, so this cost does not end on submission.
A question worth asking any provider
Ask what happens if the application is refused. 66% of applications were refused this year. A firm that has thought seriously about this will have a clear answer about how it de-risks a submission. A firm that has not will tell you their reports do not get refused.
Common questions
How much does the regulator charge for a building assessment certificate?
£312 on application, plus £156 for every hour regulator staff spend on the assessment and any third-party costs, under the 2026 to 2027 charging scheme. The total therefore depends on how much assessment time your submission needs.
How long does a building assessment certificate take?
No decision period is set in law. The regulator said in July 2026 that processing is taking twice as long as it initially expected and its residents’ guide says the process takes at least six months.
Is there a deadline once the regulator directs us to apply?
Yes. You must apply within 28 days beginning with the day the direction is given, under section 79(2). Failing to apply without a reasonable excuse is an offence.
How long does Gateway 3 take?
Regulation 41 of SI 2023/909 sets 8 weeks from receipt of a valid application, or longer if agreed in writing. The regulator’s data for June to August 2026 shows a median determination time of 20 weeks.