The Building Safety Levy is live and the completion certificate is now the pinch point

The Building Safety Levy has been in force since 1 October 2026. Most coverage has treated it as a cost line. A rate per square metre, a liability notice and a payment. The bigger change landed on 1 October itself. GOV.UK rewrote the gateway guidance so that an unpaid or unconfirmed levy now sits directly in the path of the completion certificate.

That moves the levy from a finance team’s calculation to a programme risk. This piece is about that shift. For how the levy is calculated, who pays and the exemptions, see the Building Safety Levy reference page.

Status
Principal instrument
The Building Safety Levy (England) Regulations 2025, SI 2025/1236 In force
Amended by
The Building Safety Levy (Amendment) (England) Regulations 2026, SI 2026/1034, laid 2 July 2026 under the draft affirmative procedure, made 18 September 2026
In force from
1 October 2026, both instruments
Applies to
Building control applications made on or after 1 October 2026, England only
Reference page
The Building Safety Levy, for who pays, how it is calculated and when it falls due

The levy now sits inside the gateways

The regulations always provided that an unpaid levy could block a completion certificate. What changed on 1 October is that the GOV.UK guidance for higher-risk buildings now spells out how that works in practice. It covers both ends of the project.

  • At Gateway 2, the Building Safety Regulator gathers levy information from the building control approval application.
  • When work starts on a major residential development, the regulator asks for the area of private residential units and their communal space. This comes with the notice of commencement.
  • At Gateway 3, the application must confirm that the levy has been paid or is not payable. The regulator cannot issue a completion certificate until the local council or other collecting authority confirms full payment or a valid notice of no charge.

That last step introduces a third party into the critical path. The completion certificate already depends on the regulator. It now also depends on a council confirming a payment position to the regulator. The regulator’s own data for June to August 2026 put the median Gateway 3 determination at 20 weeks against a statutory 8. A late levy confirmation or a liability figure still under review now sits on top of that.

Why the timing is the real cost

The levy falls due at the earlier of the completion notice date and first occupation. For most schemes that is before sales or lettings income arrives. Industry reaction has focused on exactly that point. It is a liability that has to be funded before the scheme generates the cash to fund it.

Put that alongside the gateway mechanics and the sequence becomes clear. The figure is fixed by decisions taken at the start of the job. It can move with design changes and spot checks during the job. It has to be paid before occupation. The council must confirm it before the certificate that permits occupation can issue. A review of a levy liability notice must be requested within 28 days. On a scheme where the figure is disputed late, that window and the Gateway 3 queue can collide.

A late change to the rate test

The other development came two weeks earlier. Amending regulations made on 18 September, SI 2026/1034, left the Schedule 3 rates untouched. They changed the test for the lower previously developed land rate. Wholly underground buildings, basements beyond the above-ground footprint and unlawful development no longer help a site reach 75%. Hardstanding, paved areas and plant now do. The other land rate is double the previously developed one, so the change can move a scheme between two figures that are far apart. The detail is on the reference page. For programme purposes, rerun any 75% calculation prepared before 18 September. Lawfulness and underground extent are now live grounds for dispute. That is the kind of disagreement that surfaces late.

What to watch

  • How collecting authorities handle confirmation. The guidance says the regulator cannot issue until the council confirms. It does not say how quickly councils will do so. That is the gap to watch on the first schemes to reach completion under the levy.
  • The first spot checks. The amendment put a five-week deadline on notifying spot checks. How collecting authorities apply it to the first applications after 1 October will show whether the audit regime is real or only on paper.
  • Previously developed land disputes. The amended test introduces lawfulness and underground extent as live questions. Expect these to be where early reviews and appeals concentrate.
  • Further amendment. The regulations were corrected once before they came into force. Errors found in use are likely to be corrected the same way. We will record any amending instrument here.

What to do about it now

Treat the levy as a programme item, not only a cost line. For each scheme with an application made on or after 1 October:

  • establish the previously developed position against the amended wording;
  • keep one gross internal area schedule with the accommodation and communal split identified; and
  • build the council’s confirmation into the Gateway 3 plan rather than assuming it will be waiting when the regulator is ready.

Plan for the confirmation step from the start.

The detail of the calculation, the exemptions and the review rights is on the Building Safety Levy reference page. The gateway mechanics are on Gateway 2 and Gateway 3.

Written 2 October 2026 and last reviewed 16 October 2026. Checked against SI 2025/1236, SI 2026/1034 made 18 September 2026, the GOV.UK pages Building control approval for higher-risk buildings and Applying for a completion certificate, both last updated 1 October 2026, GOV.UK Building Safety Levy guidance, updated 2 July 2026 and BSR building control approval application data for June to August 2026, published 15 September 2026.